|
Looking for weekly updates on street improvements?
Please follow this link!
Streets & Utilities

For a larger and more legible map, please follow this link to download the above map in PDF format (330k).
1. US Bank Retaining Wall
This project proposes to remove the existing limestone retaining wall along 80th Street and construct a new two tier modular block wall with a sidewalk at the southwest corner of Hardwood and 80th Street. Signage and landscaping will be included in this project.
Construction Updates:
Project is anticipated to bid in late spring of 2008.
Back to Top
2. Oak Cove Development
The preliminary plat for the development was approved in 2006. Grading of the site and the utilities are anticipated to be to start in 2009.
Back to Top
3. South Ridge Point Development
The proposed development was approved in March 2007. Grading of the site and utilities were installed in the late summer/early fall for the project. The final street work will be completed in early summer 2008. Also, water main will be installed on West Point Douglas from the South Ridge Point development to provide for water looping. The water main work will begin in early summer 2008.
Construction Updates:
Back to Top
4. Hamlet Park Pond Improvements Phase 3
Hamlet Park Pond will be expanded at the south end of the pond work that was completed in 2007. The pond addition will serve to provide for additional flood storage and water quality improvements for the area. This is the final phase of pond construction for the Hamlet area. Phase 3 pond construction is anticipated to start in early spring 2008.
Construction Updates:
Back to Top
5. Jamaica Roundabouts
This summer roundabout landscaping will be completed along the intersections of TH 61 ramps and Jamaica Avenue.
Landscaping of the roundabouts will start in early spring and will be completed by late summer.
Construction Updates:
For Additional Information please go the following link:
www.cottage-grove.org/project_updates_roundabout_status.shtml
Back to Top
6. Bituminous Trail Maintenance–
This project is a micro-resurfacing (liquid bituminous emulsion) to fill cracks and surface voids and to protect the bituminous pavement from sun and rain deterioration.
Trails will be closed in various segments for maintenance. Work will start in early June and will be completed by early July, weather dependent.
.
Back to Top
7. 103rd Street Bridge
A total reconstruction of the deteriorated 103rd Street bridge is planned to be completed by the summer of 2008. Construction of bridge will be by BNSF.
Construction Updates:
Construction was completed and 103rd Street opened on April 28, 2008.
Back to Top
8. 2008 Seal Coat Area
The 2008 Seal Coat Program is located in three (3) main areas of Cottage Grove.
AREA – 1 West Draw Area; north of 80th Street and west of Hardwood Avenue.
AREA – 2 Old Town Area; north of 77th Street and east of Lamar Avenue.
AREA – 3 Pine Coulee Area; south of TH 61.
Seal coating is a common preventive maintenance activity in Minnesota performed by most cities, counties, and Mn/Dot districts.
The primary reason to seal coat a bituminous pavement is to protect the pavement from the deteriorating effects of sun and water. When the pavement is exposed to sun, wind and water, the bituminous hardens, causing the pavement to become more brittle. As a result, the pavement will crack because it is unable to bend and flex when exposed to traffic and temperature changes. A seal coat combats this situation by providing a waterproof membrane which not only slows down the hardening process but also helps the pavement to shed water, preventing it from entering the gravel sub-base material.
Construction Updates:
Start date for project is July 11, 2008 and completion is anticipated to be July 29, 2008 (weather dependant).
Back to Top
9. 2008 Pavement Management
Pavement Management is a system the City has established to repair streets through various means to improve the road and increase the life expectancy of the road as a whole.
For additional information follow this link: 2008 Pavement Managment.
Back to Top
10. City Ice Arena Expansion
The proposed expansion of the ice arena will produce a 2nd NHL sheet of ice to service the Cottage Grove and surrounding area communities. The proposed 2nd sheet of ice will be in operation starting October 2008.
Construction Updates:
For additional information please follow this link.
Back to Top
|