2008 Pavement Management
The next Pavement Management Area is scheduled for construction in the spring of 2008. Pavement Management is a system the City has established to repair streets through various means to improve the road and increase the life expectancy of the road as a whole.
Thursday, May 15, 2008 Construction Update
Immanuel Ave. So. Immanuel Ave Ct. 76th Ave S. 77th Ave S.
Thursday May 15th and Friday May 16th – Replace removed concrete curb.
Monday May 19th and Tuesday May 20th – Remove manhole cover and replace with steel plate.
Monday May 19th – Mill / Remove 3 ½ inches of existing gravel surface, shape to proposed grade with road grader.
Imperial Ave. S.
Thursday May 15th, Friday 16th _ Raise manhole iron.
Imperial Ave. Ct. S.
Thursday May 15th, Friday 16th _ Raise manhole iron.
Imperial Ave. Cr. S.
Thursday May 15th, Friday 16th _ Raise manhole iron.
71st. Street S.
Thursday May 15th, Friday 16th _ Raise manhole iron.
Idsen Ave. S.
Thursday May 15th, Friday 16th _ Raise manhole iron.
71st. Street Ct. S.
Thursday May 15th, Friday 16th _ Raise manhole iron.
Hyde Ave. S. (N. of 72nd St. S.)
Thursday May 15th, Friday 16th _ Raise manhole iron.
72nd Street S.
Thursday May 15th, Friday 16th _ Raise manhole iron.
Highland Park Trail West of Idsen Ave. S.
Thursday May 15th – shape side slopes along proposed trail.
Friday May 16th, Monday May 19th and Tuesday May 20th – place top soil along proposed trail.
Tuesday May 20th - place aggregate base along proposed trail.
Highland Park East of Idsen Ave. S.
Friday May 15th, Monday May 19th existing underground utilities to be located.
80th Street Watermain Crossing
Work will be taking place on the westside of the Fire Station through May 21st.
If you have any questions or concerns the projects email address is cgpave@sehinc.com and the projects phone number is (651) 765-2990.
Xcel Energy will also be working on natural gas lines in the Pavement Management area ahead of the Pavement Management Contractors, if you have any questions or concerns with Xcel's work please give Bob Foley a call at (651) 458-1243 or Rita Duit at (651) 458-1245.
The following links are residential letters, public meeting presentations, and assesment information that was either sent to all residents or presented at public meetings that affect the 2008 Pavement Management Area:
Resident Letter - Updated 10/10/07
Assessment Policy
2008 Pavement Management Area -Updated 10/10/07
Neighborhood Meeting Powerpoint Presentation -Updated 10/31/07
December 5, 2007 Council Action Memo -Updated 12/4/07
Assessment Survey Memo -Updated 12/4/07
Public Hearing Power Point Presentation -Updated 12/7/07
Right of Entry Letter -Updated 2/29/08
Right of Entry Map -Updated 2/29/08
Right of Entry Form -Updated 2/29/08
2008 Pavement Management Neighborhood Meeting -Updated 3/21/08
Traffic Control Analysis for 2008 Pavement Management Area -Updated 4/23/08
Residents interested in replacing or reconstruction their driveway are required to get a permit from the City of Cottage Grove Buiding Department for the work at 651-458-2804.
Project Schedule |
| August 2007 |
Final Evaluation and Data Collection |
| September 2007 |
Preparation of Feasibility Report and Report to City Council |
| October 29, 2007 |
Neighborhood Meeting (see above for Presentation) |
| November 7, 2007 |
Present Feasibility Report to Council & Order Public Improvement Hearing |
| December 5, 2007 |
City Council Holds Public Improvement Hearing & Orders Public Improvements |
| January 14, 2008 |
City Council Approves Plans & Specs, Authorizes Advertisement for Bids |
| February 12, 2008 |
City Receives Bids |
| February 20, 2008 |
City Council Awards Contract |
| April/Early May 2008 |
Contractor Begins Work |
| August 30, 2008 |
Substanial Completion |
| September 3, 2008 |
City Council Orders Assessment Hearing |
| September 30, 2008 |
Final Completion |
| October 1, 2008 |
City Council Holds Assessment Hearing & Adopts Assessment Role |
| |
|
|